Top 20 Reportable Items (RIs) raised at pre-CML (completion) inspections — covering commissioning certificates, EPC, snagging, and handover readiness.
Check all snagging items from previous NHBC inspections are resolved and signed off
Verify all internal decoration is complete, consistent and to acceptable finish standard
Confirm all sanitary ware is fitted, sealed and operational (taps, WCs, showers, baths)
Check kitchen units, worktops, splashbacks and appliances are installed and operational
Inspect all flooring for damage, gaps, lippage and check thresholds / transitions are secure
Verify all external works complete — paths, drives, fencing, turfing / seeding, meter boxes
Check meter boxes fitted, connections live and all service supplies commissioned
Confirm fire detection system tested, commissioned and certificate available on site
Verify EPC certificate has been issued and rating matches SAP calculation
Check all windows and doors operate freely with locks, handles and restrictors functional
Confirm all gas, electric and water installations have valid commissioning certificates
Verify Part P electrical certificate and any gas safe certificates are available on site
Check external drainage gullies are clear, covers sit flush and surface water drains freely
Confirm all ironmongery is fitted — door closers, latches, letterboxes, house numbers
Verify all mastic / sealant joints are complete around baths, showers, worktops and externally
Check loft insulation coverage matches specification with no displaced or missing areas
Confirm any communal areas (apartments) are complete — lighting, fire doors, signage
Verify boiler / heating system has been commissioned with certificate and user guide provided
Check all party wall / sound insulation details are complete and match Robust Details or approved plan
Confirm property is clean, safe and ready for handover — all builder debris removed
ProPlot's audit feature includes these pre-cml checks as interactive helpers — tick items off, attach photos, and share reports with your inspector in one tap.
Join the BetaDiscover how ProPlot covers every corner of UK site management.
Part L photographic evidence requirements.
Cut evening admin and automate reporting.
Build, slip and share 52-week programmes.
NHBC inspections, Part L evidence and audit trails.
Offline audits, GPS snagging and contractor portals.
Get practical tips for UK site managers — programme hacks, compliance shortcuts and feature updates. No spam.