Maximum
    England

    Limiting air permeability for a new dwelling

    8 m³/(h·m²) at 50 Pa

    New dwelling air pressure test at completion

    Worst air permeability allowed on test for a new dwelling, regardless of the design figure used in the calculation.

    Basis in regulation

    How to check it on site

    Walk the airtightness line before plaster: service penetrations, loft hatch, and the joist ends at separating walls are where the result is won or lost.

    Common failure

    Design figure of 5 assumed in the calculation but a tested result well above it, forcing a re-test or remedial sealing after decoration.

    Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.