Maximum
    England

    Spacing between drainage access points

    45 m

    Straight run of buried drain between access points

    Greatest distance permitted between rodding points, access fittings or inspection chambers on a drain run.

    Basis in regulation

    How to check it on site

    Walk the drain layout against the as-built drawing before covers are set to finished level. Confirm every change of direction and junction can be rodded.

    Common failure

    Bends added on site to dodge an obstruction, leaving a length that cannot be rodded from either end.

    Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.