Ductwork Fixing and Condensate Management
750 mm
MVHR ductwork must be securely fixed at appropriate intervals to prevent sagging, typically no more than 750mm apart, or as per manufacturer guidelines
MVHR ductwork must be securely fixed at appropriate intervals to prevent sagging, typically no more than 750mm apart, or as per manufacturer guidelines. Horizontal duct runs should be installed to a slight fall towards a condensate outfall to prevent water accumulation, while external wall penetrations must slope downwards to prevent water ingress. Ductwork should also be isolated from building elements to minimise noise transfer.
Basis in regulation
How to check it on site
Verify ductwork is securely fixed at correct intervals, horizontal runs fall correctly for drainage, and penetrations slope outwards; check for isolation from surfaces.
Common failure
Insufficient fixing causes sagging, leading to condensate traps and air pressure loss, while direct contact with surfaces can transmit noise.