Minimum
England
Minimum cover for mechanical compaction
150 mm
Before mechanical compaction of trench backfill, a minimum of 150mm of material should be placed above the pipe to prevent direct damage.
Before mechanical compaction of trench backfill, a minimum of 150mm of material should be placed above the pipe to prevent direct damage.
Basis in regulation
BS EN 1610
Read the source
How to check it on site
Verify that there is at least 150mm of cover over the pipe before any mechanical compaction is started.
Common failure
Starting mechanical compaction too early, damaging the installed pipe.
Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.