Minimum
    England

    Minimum cover for mechanical compaction

    150 mm

    Before mechanical compaction of trench backfill, a minimum of 150mm of material should be placed above the pipe to prevent direct damage.

    Before mechanical compaction of trench backfill, a minimum of 150mm of material should be placed above the pipe to prevent direct damage.

    Basis in regulation

    How to check it on site

    Verify that there is at least 150mm of cover over the pipe before any mechanical compaction is started.

    Common failure

    Starting mechanical compaction too early, damaging the installed pipe.

    Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.