Temperature limits and protection for masonry
3 °C
Brickwork and blockwork should generally not be laid when the air temperature is below 3°C and falling; work can resume when temperatures rise to 1°C with an expectation of exceeding 3°C
Brickwork and blockwork should generally not be laid when the air temperature is below 3°C and falling; work can resume when temperatures rise to 1°C with an expectation of exceeding 3°C. Materials damaged by frost must not be used. Additional insulation and covers, such as polyethylene sheeting with an air gap, are required in severe cold, potentially combined with heaters, and frost protection may be needed for several days.
Basis in regulation
BS EN 1996-1-1
Read the source
How to check it on site
Verify air temperatures are suitable for masonry work, materials are unfrozen, and new masonry is adequately protected by covers and insulation.
Common failure
Laying masonry in freezing conditions, causing mortar to freeze, losing strength and bond, or using frozen blocks/bricks.
Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.