Foundation depth during cold weather
450 mm
When construction occurs in cold weather, foundations should be at least 450mm below existing ground level, or adequate measures must be taken to prevent ground freezing
When construction occurs in cold weather, foundations should be at least 450mm below existing ground level, or adequate measures must be taken to prevent ground freezing. If the finished ground level will be higher than the existing, the foundation depth requirement applies from the existing ground level.
Basis in regulation
How to check it on site
Check foundation depth relative to existing ground level, particularly during cold periods, and confirm any ground protection measures.
Common failure
Excavated trenches are left exposed in cold weather, allowing the bearing strata to freeze before concrete pour.