Clear cavity behind the breather membrane in timber frame
50 mm
Clear residual width, measured from the face of the breather membrane to the back of the outer leaf
Every figure for this topic is on one page: Timber frame stud spacing, sheathing and restraint straps
Read the full answerA drained and ventilated cavity is needed between the breather membrane and the masonry cladding so that water crossing the outer leaf can run away rather than reach the frame.
Basis in regulation
How to check it on site
Check the cavity is clear of mortar snots at each lift and that the gap is maintained where ties and services cross.
Common failure
Mortar droppings bridging the cavity onto the membrane, wetting the sheathing behind.