Maximum
England
Timber moisture content before closing up
20 %
Measured with a calibrated meter at several points, including sole plates and the base of studs
Structural timber that is closed in wet will shrink and can support mould, so it should be dried back before boarding.
Basis in regulation
How to check it on site
Take readings low down on the frame where water collects, and record them with the pre-plaster photographs.
Common failure
Frames closed in after a wet erection period, giving shrinkage cracking and nail pops later.