Maximum
    England

    Timber moisture content before closing up

    20 %

    Measured with a calibrated meter at several points, including sole plates and the base of studs

    Structural timber that is closed in wet will shrink and can support mould, so it should be dried back before boarding.

    Basis in regulation

    How to check it on site

    Take readings low down on the frame where water collects, and record them with the pre-plaster photographs.

    Common failure

    Frames closed in after a wet erection period, giving shrinkage cracking and nail pops later.

    Effective from 22 August 2026. Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.