Building settlement limits on fill
25 mm
Total settlement of a building foundation on engineered fill should generally not exceed 25mm over its 60-year design life
Total settlement of a building foundation on engineered fill should generally not exceed 25mm over its 60-year design life. Crucially, the differential settlement (tilt or distortion) between any parts of the foundation must be limited, typically not exceeding 1 in 400. These limits prevent aesthetic damage and ensure structural stability.
Basis in regulation
BS EN 1997-1
Read the source
How to check it on site
Review the geotechnical report to confirm predicted settlement values are within acceptable limits for the proposed foundations.
Common failure
Underestimation of differential settlement, leading to significant cracking and distortion of the building superstructure.
Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.