    Damp-proof membrane lap and seal

    150 mm

    Ground-supported slab, membrane above or below the concrete

    Every figure for this topic is on one page: Cavity trays and DPC: where are they needed and how high?

    Read the full answer

    Minimum lap where sheets of damp-proof membrane meet, and the requirement to seal the membrane to the damp-proof course.

    Basis in regulation

    How to check it on site

    Check laps before concrete is poured or the slab is covered. Every lap should be taped or welded, and the membrane carried up and sealed into the DPC at the perimeter.

    Common failure

    Membrane torn by reinforcement or barrow traffic, or finished short at the perimeter so the slab edge stays open to ground moisture.

    Last updated 23 August 2026. This is our editorial summary of publicly available regulation, not building control approval or a warranty determination.