First fix: what good looks like

    Electrical, plumbing and mechanical first fix.

    What good looks like

    First fix: what good looks like

    Services routed within the zones the structure allows, fixed and supported properly, tested where they will be buried, and set out so second fix lands where the drawing says.

    First fix is where the structure and the services meet, and where each can quietly ruin the other. The structural rules are simple and absolute: cut joists and studs only within the permitted zones, and never cut an engineered joist outside its printed knockouts. Pipework is judged on gradient, support and joint access. Branch discharge pipes need a fall within the permitted range and a route that keeps within the maximum branch length, or the trap will siphon and the customer will smell it. Everything buried behind plaster should be tested and recorded first — pressure test on the pipework, continuity and insulation resistance on the circuits — because the cost of finding a fault afterwards is a redecoration, not a repair.

    Basis in regulation

    Before you start

    Before you start: first fix

    Checks to clear before the trades open up the structure.

    Walk the plot with the joist and truss layout and mark the permitted notch, hole and knockout zones before anyone drills. Set out kitchen, bathroom and utility positions on the floor so socket, waste and stack positions are fixed once, not moved at second fix. Confirm the stair opening gives the required headroom before the stair is ordered, and check hearth and flue positions against the appliance actually being installed. Agree who seals which penetrations for the air barrier, and have grommets, collars and fire stopping on site before the trade starts.

    Basis in regulation

    Key requirements

    SVP and kitchen extractor routing/sealing

    Soil vent pipes (SVPs) should be routed to allow for proper function and maintenance, potentially including turning into the roof void for visibility or routing to a higher level. A frost cap is installed on the SVP terminal at the pre-plaster stage to protect against blockages, ensuring its height

    Soil vent pipes (SVPs) should be routed to allow for proper function and maintenance, potentially including turning into the roof void for visibility or routing to a higher level. A frost cap is installed on the SVP terminal at the pre-plaster stage to protect against blockages, ensuring its height allows for insulation without obstruction. Kitchen extractor runs require specific components, must be adequately supported along their length, and properly sealed to maintain airtightness and prevent condensation.

    Basis in regulation

    Stair string fixing methods

    The safe and stable installation of a staircase requires the stringers to be robustly fixed to adjacent structures, whether masonry or timber stud walls. Fixings, typically screws of adequate length and diameter, should penetrate into solid material, with their spacing and type determined by the wal

    The safe and stable installation of a staircase requires the stringers to be robustly fixed to adjacent structures, whether masonry or timber stud walls. Fixings, typically screws of adequate length and diameter, should penetrate into solid material, with their spacing and type determined by the wall construction and stair design. It is common practice to fix the string at the top and bottom first, then progressively fill in the intermediate fixings, ensuring that the staircase is fully secure before use.

    Basis in regulation

    Staircase Integration and External Use

    Staircase fixings must not compromise the fire resistance or acoustic performance of the supporting structure. Landings require proper support and framing to securely transmit loads, providing stable attachment points for all staircase elements without undue movement. External timber staircases and

    Staircase fixings must not compromise the fire resistance or acoustic performance of the supporting structure. Landings require proper support and framing to securely transmit loads, providing stable attachment points for all staircase elements without undue movement. External timber staircases and landings must be constructed from appropriately preservative-treated or naturally durable timber, following guidance from organisations like the Timber Decking and Cladding Association.

    Basis in regulation

    Pipework fixing and protection

    Pipework must be adequately supported and secured using appropriate clips installed at regular intervals to prevent movement and ensure stability. Care must be taken to ensure pipes are not positioned where they can be inadvertently damaged by subsequent fixings, such as plasterboard screws, particu

    Pipework must be adequately supported and secured using appropriate clips installed at regular intervals to prevent movement and ensure stability. Care must be taken to ensure pipes are not positioned where they can be inadvertently damaged by subsequent fixings, such as plasterboard screws, particularly where they run close to structural elements or drylining channels. Proper planning of pipe runs minimises the risk of damage during later stages of construction.

    Basis in regulation

    Extractor ducting specification and installation

    Mechanical ventilation systems, including extractor fans, must utilise ducting of the correct size and type to ensure efficient airflow and compliance with building regulations. The system should be installed in accordance with the ventilation design, and rigid ducting is generally preferred, especi

    Mechanical ventilation systems, including extractor fans, must utilise ducting of the correct size and type to ensure efficient airflow and compliance with building regulations. The system should be installed in accordance with the ventilation design, and rigid ducting is generally preferred, especially for longer runs, to minimise airflow resistance and prevent condensation. Flexible ducting should be kept as short and taut as possible to maintain performance.

    Basis in regulation

    Radiator valve installation and sealing

    Radiator valves and connections must be installed correctly and securely to ensure a leak-free system. When fixing radiator bosses or connections through plasterboard, it is good practice to provide a solid backing, such as OSB, to create a tight seal against foam gaskets and prevent movement, ensur

    Radiator valves and connections must be installed correctly and securely to ensure a leak-free system. When fixing radiator bosses or connections through plasterboard, it is good practice to provide a solid backing, such as OSB, to create a tight seal against foam gaskets and prevent movement, ensuring long-term integrity and air tightness around the penetration. This solid backing helps to resist compressive forces and potential damage to the plasterboard.

    Basis in regulation

    Heat pump system specification

    Heat pump systems should primarily be procured as a complete package from a single manufacturer to ensure compatibility and optimal performance. If components from various manufacturers are used, their compatibility must be explicitly confirmed. The selected heat pump must meet or exceed 100% of the

    Heat pump systems should primarily be procured as a complete package from a single manufacturer to ensure compatibility and optimal performance. If components from various manufacturers are used, their compatibility must be explicitly confirmed. The selected heat pump must meet or exceed 100% of the calculated space heating demand under winter conditions, accounting for defrost cycles, with supplementary electric heating only engaging when necessary.

    Basis in regulation

    Kitchen appliance utility connections

    Utility connections for kitchen appliances, such as gas outlets for hobs, must be positioned accurately to ensure functionality and accessibility once units are installed. The height of the gas pipe for a hob typically needs to be coordinated with the kitchen design to allow for access panels above

    Utility connections for kitchen appliances, such as gas outlets for hobs, must be positioned accurately to ensure functionality and accessibility once units are installed. The height of the gas pipe for a hob typically needs to be coordinated with the kitchen design to allow for access panels above the appliance. When coring for flues, it is essential to first check for the presence of cavity trays to prevent damage to the damp proofing system.

    Basis in regulation

    Stairwell handrail pattress installation

    To ensure secure fixing of handrails in stairwells, especially where they are to be mounted on masonry or plasterboarded stud walls, appropriate pattressing must be installed during the first-fix stage. These timber or OSB backing pieces should be fitted flush within the studwork or fixed to the mas

    To ensure secure fixing of handrails in stairwells, especially where they are to be mounted on masonry or plasterboarded stud walls, appropriate pattressing must be installed during the first-fix stage. These timber or OSB backing pieces should be fitted flush within the studwork or fixed to the masonry. Correctly installed pattressing not only provides a strong anchorage point but also reduces the risk of inadequate temporary handrail support during construction.

    Basis in regulation

    Modifying engineered timber joists for services

    I-joists are typically supplied with preformed holes, and no additional notching or drilling should be undertaken without the express approval of the manufacturer. For metal web joists, services should be routed through the spaces between the metal webs, and some conduits may need to be installed be

    I-joists are typically supplied with preformed holes, and no additional notching or drilling should be undertaken without the express approval of the manufacturer. For metal web joists, services should be routed through the spaces between the metal webs, and some conduits may need to be installed before the joists are fixed in place. Lightweight steel framing systems must always be installed according to the manufacturer's guidelines.

    Basis in regulation

    Fixing and Protection of Services and Components

    Any notching, drilling, or chasing of structural components for services must comply with established guidance or be specifically engineered to maintain structural integrity. Fixings, supports, and brackets for mechanical systems must be robust enough to accommodate all static and dynamic loads, pre

    Any notching, drilling, or chasing of structural components for services must comply with established guidance or be specifically engineered to maintain structural integrity. Fixings, supports, and brackets for mechanical systems must be robust enough to accommodate all static and dynamic loads, preventing bimetallic corrosion through material compatibility or isolation. Adequate corrosion protection is essential, with specific recommendations for coastal environments.

    Basis in regulation

    Insulation for heating and hot water pipework

    Pipework serving space heating and hot water systems must be insulated wherever it runs outside the heated building envelope. Additionally, insulation is required for all primary flow and return pipework from the heat source to the hot water cylinder, including when passing through intermediate floo

    Pipework serving space heating and hot water systems must be insulated wherever it runs outside the heated building envelope. Additionally, insulation is required for all primary flow and return pipework from the heat source to the hot water cylinder, including when passing through intermediate floor voids. Any secondary return circuits and pipework within 1 metre of the hot water cylinder (flow, return, hot, cold distribution, or feed pipes) also require insulation to meet minimum specified requirements.

    Basis in regulation

    Key requirements: first fix

    The first fix requirements most often picked up at the pre-plaster inspection.

    Notches and holes in joists and studs only within the permitted zones, with engineered joists cut only at printed knockouts. Branch discharge pipes laid within the permitted gradient range and within the maximum branch length, with rodding access at bends. Pipework clipped at the specified centres and supported at every change of direction. Cables run in permitted safe zones and protected where buried shallow. Smoke and heat alarm positions set out to the required distances and interlinked. Constructional hearth and flue details correct for the appliance being fitted. Pressure and electrical tests completed and recorded before anything is boarded over. Air barrier penetrations sealed as the work proceeds.

    Basis in regulation

    Boiler pipework and gas pipe recessing

    Boiler pipework must be accurately positioned during first fix, often utilising fixing templates for precise installation. Boilers are typically mounted on external walls to accommodate flues, and concealed flues are generally not permitted without specific considerations. Where plastic-coated gas p

    Boiler pipework must be accurately positioned during first fix, often utilising fixing templates for precise installation. Boilers are typically mounted on external walls to accommodate flues, and concealed flues are generally not permitted without specific considerations. Where plastic-coated gas pipes are recessed into a wall, they must be adequately protected, for example, by being covered with mortar and then securely 'dabbed' in place when plastered. All pipework, including gas lines, must undergo testing prior to the boiler being fitted.

    Basis in regulation

    MVHR Ductwork Materials and Installation

    MVHR ductwork should be constructed from rigid or semi-rigid materials appropriate for the system and installed to achieve satisfactory performance over its lifespan. Routing should be as direct as possible, and any alterations to structural elements required for duct paths must comply with relevant

    MVHR ductwork should be constructed from rigid or semi-rigid materials appropriate for the system and installed to achieve satisfactory performance over its lifespan. Routing should be as direct as possible, and any alterations to structural elements required for duct paths must comply with relevant building regulations or manufacturer guidance. The system's materials and design should not negatively impact the building's overall performance.

    Basis in regulation

    Stair positioning and packing for finishing

    Staircases must be accurately positioned and securely fixed, ensuring treads are level and square to newel posts and other components to provide a safe and aesthetically pleasing final assembly. Where stair strings run alongside masonry walls, a continuous packer or gap should be maintained to allow

    Staircases must be accurately positioned and securely fixed, ensuring treads are level and square to newel posts and other components to provide a safe and aesthetically pleasing final assembly. Where stair strings run alongside masonry walls, a continuous packer or gap should be maintained to allow for the thickness of finishes, such as plasterboard, to achieve a flush appearance. Careful alignment is particularly critical for winder treads.

    Basis in regulation

    Critical dimensions at this stage

    Browse all critical dimensions
    England
    Low-rise traditional

    Original editorial guidance based on publicly available Approved Documents. Not building control approval, a warranty determination, or a substitute for the full source document.

    We use cookies to keep you logged in and improve ProPlot. Privacy Policy