    Build programme builder

    This is the real ProPlot programme builder, running live in your browser. Auto-generate the full build sequence across every plot, then edit any stage yourself — durations, dates, order — and slip a date to see the knock-on effect. No account, nothing saved.

    Sample data from Willow Grange, a fictional 48-plot development in Nantwich, Cheshire. Everything here is fully editable in your browser — changes are never saved. Create a free account to keep your own programme.

    Willow Grange — sample site, 6 plots, masonry, trench and piled foundations. Every edit stays in this browser tab.

    Start here — press Auto-generate programme to lay the full stage sequence across every plot.

    Schedule

    Sep 7 - Nov 29, 2026
    PlotType
    Mon
    Sep 7
    Tue
    Sep 8
    Wed
    Sep 9
    Thu
    Sep 10
    Fri
    Sep 11
    Sat
    Sep 12
    Sun
    Sep 13
    Mon
    Sep 14
    Tue
    Sep 15
    Wed
    Sep 16
    Thu
    Sep 17
    Fri
    Sep 18
    Sat
    Sep 19
    Sun
    Sep 20
    Mon
    Sep 21
    Tue
    Sep 22
    Wed
    Sep 23
    Thu
    Sep 24
    Fri
    Sep 25
    Sat
    Sep 26
    Sun
    Sep 27
    Mon
    Sep 28
    Tue
    Sep 29
    Wed
    Sep 30
    Thu
    Oct 1
    Fri
    Oct 2
    Sat
    Oct 3
    Sun
    Oct 4
    Mon
    Oct 5
    Tue
    Oct 6
    Wed
    Oct 7
    Thu
    Oct 8
    Fri
    Oct 9
    Sat
    Oct 10
    Sun
    Oct 11
    Mon
    Oct 12
    Tue
    Oct 13
    Wed
    Oct 14
    Thu
    Oct 15
    Fri
    Oct 16
    Sat
    Oct 17
    Sun
    Oct 18
    Mon
    Oct 19
    Tue
    Oct 20
    Wed
    Oct 21
    Thu
    Oct 22
    Fri
    Oct 23
    Sat
    Oct 24
    Sun
    Oct 25
    Mon
    Oct 26
    Tue
    Oct 27
    Wed
    Oct 28
    Thu
    Oct 29
    Fri
    Oct 30
    Sat
    Oct 31
    Sun
    Nov 1
    Mon
    Nov 2
    Tue
    Nov 3
    Wed
    Nov 4
    Thu
    Nov 5
    Fri
    Nov 6
    Sat
    Nov 7
    Sun
    Nov 8
    Mon
    Nov 9
    Tue
    Nov 10
    Wed
    Nov 11
    Thu
    Nov 12
    Fri
    Nov 13
    Sat
    Nov 14
    Sun
    Nov 15
    Mon
    Nov 16
    Tue
    Nov 17
    Wed
    Nov 18
    Thu
    Nov 19
    Fri
    Nov 20
    Sat
    Nov 21
    Sun
    Nov 22
    Mon
    Nov 23
    Tue
    Nov 24
    Wed
    Nov 25
    Thu
    Nov 26
    Fri
    Nov 27
    Sat
    Nov 28
    Sun
    Nov 29
    Plot 01
    Masonry
    External
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    External Doors/Windows
    External Doors/Windows
    Internal
    Plot 02
    Masonry
    External
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Drainage
    Drainage
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    External Doors/Windows
    External Doors/Windows
    Internal
    Plot 03
    Masonry
    External
    Pour Concrete
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Drainage
    Drainage
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    External Doors/Windows
    External Doors/Windows
    Internal
    Plot 04
    Masonry
    External
    Piling Mat
    Piling Mat
    Drive Piles
    Drive Piles
    Drive Piles
    Pile Caps & Reinforcement
    Pile Caps & Reinforcement
    Inspection
    Pour Concrete
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Drainage
    Drainage
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    External Doors/Windows
    External Doors/Windows
    Internal
    Plot 05
    Masonry
    External
    Piling Mat
    Piling Mat
    Drive Piles
    Drive Piles
    Drive Piles
    Pile Caps & Reinforcement
    Pile Caps & Reinforcement
    Inspection
    Pour Concrete
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Drainage
    Drainage
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    Internal
    Plot 06
    Masonry
    External
    Dig Foundations
    Dig Foundations
    Dig Foundations
    Inspection
    Pour Concrete
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Substructure Block & Brickwork
    Drainage
    Drainage
    Blocks & Beam
    Blocks & Beam
    Concrete Floor
    Concrete Floor
    Scaffolding Mat
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Brickwork
    1st Lift Scaffold
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Brickwork
    2nd Lift Scaffold
    Joists and Flooring
    Joists and Flooring
    Superstructure Inspection
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Brickwork
    3rd Lift Scaffold
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Brickwork
    4th Lift Scaffolding
    Gables Scaffolding
    Roof Plate
    Roof Plate
    Crane
    Roof Construction
    Roof Construction
    Roof Construction
    Roof Construction
    Gables
    Gables
    Roof Inspection
    Felt and Batton
    Felt and Batton
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Roof Tiling
    Solars
    Gutters
    Strike Scaffold
    External Doors/Windows
    Internal

    Keep this programme

    A free account saves the site, exports the programme to Excel, prints it to A4 and shares a live link with your contractors.

    Create a free account

    How the build programme works

    A traditional masonry house runs through a well-established stage sequence, and the value of a programme is not the list itself — it is knowing which plot is on which stage today, and what the knock-on effect is when one of them slips. Most small and mid-sized UK housebuilders still run this on a spreadsheet that is accurate on the Monday it was printed and wrong by Wednesday.

    ProPlot builds the sequence once, applies it across every plot, and then lets the site manager update it from a phone while walking the site. The sandbox above is the genuine article: add a plot, run the auto-generate wizard, and the full stage sequence lays itself out across working days, skipping weekends and UK bank holidays.

    The four statuses that matter

    Complete means the stage is finished and, where evidence is required, photographed. In progress is work happening now. Waiting is the important one — the gang is ready but blocked by a delivery, a preceding trade or an inspection. Behind means the stage has passed its planned window, and ProPlot requires a reason and photographic evidence before it accepts that status, so the audit trail holds up months later when the delay is being argued about.

    Worked example: a two-day masonry slip

    Superstructure to eaves on plots 05 and 06 is planned for weeks 6 to 9. Two days are lost to wind — logged automatically against the weather record — so the stage is marked behind with the delay reason attached. Roof structure, planned for week 10, moves out by the same two days, and every stage downstream of it shifts with it. The CML date on the plot tracker updates from 09 November to 11 November, and the reason is still attached to it in December when the board report is produced. Try it in the sandbox: long-press or right-click a scheduled day and push the programme.

    Why this beats a spreadsheet

    A spreadsheet holds the plan. It does not hold the reason a stage moved, the photo proving the trench was correct before the pour, or the message sent to the bricklayer on the Tuesday. Because the programme, the diary, the snag list and the photographic evidence all sit against the same plot in ProPlot, the history of a plot is reconstructable in one click rather than assembled from three inboxes and a camera roll.

    Editing the programme yourself

    Auto-generate gives you a starting sequence, not a locked plan. Tap any scheduled stage in the board above to open it and change its dates or duration — the stages that follow re-space around the change rather than leaving a hole in the programme. Long-press a scheduled day on a phone, or right-click on a desktop, and the action sheet gives you the quick moves: mark the stage complete, set it waiting, push it out by a day, or split the day between two trades.

    The stage list itself is yours to shape. Add a stage this site actually runs, rename one to match the words your trades use, drag it into the right position in the sequence, or delete the stages that never apply — a timber-frame site should not be carrying masonry stages it will never book. Durations are set per stage and per house type, so a four-bed detached and a two-bed terrace do not have to share a brickwork duration. Changes you make to the sequence become your template, so the next site starts from your programme rather than a generic one.

    Weekends are non-working by default, and every UK bank holiday is already excluded from the working-day calculation. When you work a Saturday to claw back a delay, long-press that date to switch it on as a working day and the programme recalculates around it.

    A typical masonry stage sequence

    • Wk 1

      Site strip & setting out

      Groundworks — J. Hale Civils

      Complete
    • Wk 2–3

      Foundations / trench fill

      Groundworks — J. Hale Civils

      Complete
    • Wk 3

      Drainage below slab

      Groundworks — J. Hale Civils

      Complete
    • Wk 4

      Blockwork to DPC

      Masonry — Ridgeway Brickwork

      Complete
    • Wk 5

      Beam & block floor

      Masonry — Ridgeway Brickwork

      Complete
    • Wk 6–9

      Superstructure to eaves

      Masonry — Ridgeway Brickwork

      In progress
    • Wk 10

      Roof structure & trusses

      Carpentry — Two Oaks Joinery

      Waiting
    • Wk 11

      Roof tiling & leadwork

      Roofing — Crestline Roofing

      Not started
    • Wk 12

      Windows & external doors

      Glazing — Sherwood Windows

      Not started
    • Wk 13–14

      First fix plumbing & electrics

      M&E — Barnett Services

      Not started
    • Wk 15

      Insulation & pre-plaster check

      Site team

      Not started
    • Wk 16–17

      Plasterboard & skim

      Drylining — Cheshire Plastering

      Not started
    • Wk 18–21

      Second fix & decoration

      Finishing — multiple trades

      Not started
    • Wk 22

      Pre-CML inspection

      Site team + NHBC

      Not started

    Where the programme connects

    The programme is one view of the plot. The same dates drive the plot progress tracker, the day's work shows up in the daily site diary, and defects raised against a stage land on the snag list with the photo evidence attached. When you are ready to keep a programme, create a free account.

    Frequently asked questions

    Can I really use the build programme without an account?
    Yes. The board on this page is the real ProPlot programme builder running entirely in your browser. Add plots, auto-generate a programme, drag stages, slip dates — nothing is sent to our servers and nothing is saved. Refresh the page and the sample site comes back.
    How does the auto-generate programme button work?
    Press Auto-generate programme and the wizard asks for a start date, the build type, the foundation type and which plots to apply it to. ProPlot then lays the full stage sequence across every selected plot using your stage durations, spacing the work over working days only and skipping weekends and UK bank holidays. A 48-plot development is programmed in a couple of minutes instead of a week in Excel.
    Can I edit the stage durations after auto-generating?
    Yes — every stage is editable after generation. Open a stage to change its duration or dates, and the stages that follow it re-space around the change. Nothing is locked by the generator; it only gives you a sensible starting sequence.
    Can I delete stages I do not use and add my own?
    Yes. Stages can be added, renamed, reordered and removed per project, so a timber-frame site is not carrying masonry stages it will never run. Custom stages are saved to your template library so the next site starts from your own sequence.
    What happens when a stage slips?
    Marking a stage behind flags it against the plot and, where stages are linked, pushes the dependent work out. Delay reasons — weather, materials, labour, design — are recorded with the date so the reason for a slipped CML date is still visible months later.
    Does it handle weekends and bank holidays?
    UK bank holidays are built in and excluded from working days automatically. Weekends are non-working by default and can be switched on per date when you are working a Saturday to claw back a delay.
    Can I export or print the generated programme?
    Yes, from a free account. The programme exports to Excel and prints to a clean A4 programme sheet for the site cabin wall. Exports are the one thing the sandbox cannot do, because the file has to be generated against a saved project.
    Can contractors see the programme?
    You can share a read-only link with a subcontractor showing only their trade's upcoming work. They open it in a browser — no app, no login, no seat cost. Sharing needs a free account, since the link has to live somewhere.

    Run this on your own site — free

    ProPlot is free to use. No card, no trial clock, no per-seat pricing. Create an account and set up your first development in a couple of minutes.