NHBC Chapter 6.1–6.10 · 22 checks · proplot.co.uk
Masonry superstructure checks — cavity width, wall ties, DPC, lintels and bearings, cavity trays, movement joints, party wall fire stopping and restraint straps.
22 checks · Reviewed by the ProPlot site team · How we write these guides
In short
The superstructure inspection covers the masonry shell as it rises. The inspector checks cavity width and cleanliness, wall tie type, spacing and embedment, DPC position and continuity, lintels and their bearings, cavity trays and weep holes, insulation fit, and fire stopping and cavity barriers at compartment lines.
Superstructure is where a warranty inspector spends the most time, because a masonry shell hides more than any other stage. Wall ties, cavity trays, lintel bearings and insulation continuity all end up behind a finished face, and a defect found at handover means taking brickwork down. Most providers inspect at least once during the superstructure — often at first lift and again at wall plate.
The inspector is checking three things at once: structure, weathertightness and fire. Structure means tie centres and type, lintel specification and bearing, restraint straps to gables and floors, and the bond and coursing of the masonry itself. Weathertightness means DPC height, cavity tray and stop end details over every opening, weep holes, and a cavity kept clear of mortar droppings. Fire means the separating wall carried tight to the underside of the roof with the cavity barriers and stopping actually installed rather than intended.
The list below follows the order a bricklayer builds in, so you can walk the scaffold with it. Photograph cavity trays, ties and insulation before the next lift goes on — concealed-work photographs are the cheapest insurance on the site.
When it happens
During the masonry lifts and again once the wall plate is strapped down, before the roof structure closes off access to the cavity and the party wall head.
Who inspects
Warranty provider inspector, building control, and on timber-frame or steel-frame hybrids the frame supplier's own erection check.
If it fails
Superstructure failures are the most disruptive to fix. Missing ties or trays mean cutting out and rebuilding sections of the outer leaf, usually with the scaffold already struck and the roof on.
Concealed work cannot be re-photographed later. Take these before the element is covered and file them against the plot.
A Reportable Item (RI) is a defect the inspector records against the plot. NHBC weigh each one by its Damage Potential, and the score feeds your site's Construction Quality Review. These are the ones raised most often here:
The measurable values most often argued about at the superstructure visit, each traced to an openly published source. Take a tape to the ones that apply before you book.
| What | Value | Type |
|---|---|---|
| Air temperature limits for laying masonryMasonry and render work in cold weather.Check hessian or frost blankets are on the work at the end of the shift, not folded on the scaffold. | Stop at 3 °C and falling; do not restart below 1 °C rising | Minimum |
| Background ventilator equivalent areaDwelling with background ventilators, including window replacement workCheck the ventilator equivalent area printed on the product data against the window schedule room by room — not the physical slot size. | 8000 mm² equivalent area to habitable rooms; 4000 mm² to kitchens, utility rooms and bathrooms | Minimum |
| Cavity drainage and DPC extensionCavities in external walls must extend at least 150mm below the damp-proof course (DPC) level to allow for proper drainage and collection of moistureCheck that the cavity extends sufficiently below the DPC and that weep holes are correctly spaced, unobstructed, and clear of mortar. | 150 mm | Minimum |
| Cavity tray upstand heightCavity tray over an opening, abutment or cavity interruptionPhotograph each tray before the next lift covers it. Confirm the tray rises at least 150 mm, is continuous, and has stop ends and weep holes at each end. | 150 mm | Minimum |
| Cavity wall tie horizontal spacing (full-fill insulation)For cavity walls incorporating full-fill insulation, wall ties must be placed at maximum 900mm horizontal centresVerify that horizontal tie spacing for full-fill insulated cavities does not exceed 900mm. | 900 mm | Maximum |
| Chimney wall thickness and constructionThe minimum wall thickness for block, brick, or stone chimneys, excluding flue lining, is typically 100mmCheck the thickness of chimney walls, ensuring 100mm minimum for general construction, and 200mm for compartment walls, and verify factory-made flues are installed per manufacturer's instructions. | 100 mm | Minimum |
| Concrete Placement Conditions and TechniqueConcrete should not be placed if its temperature at the point of use is below 5°C, as fresh concrete is vulnerable to frost damageCheck concrete temperature before placement, confirm no standing water in the pour area, and observe that concrete is placed continuously and directly to minimise handling and segregation. | 5 °C | Exact |
| Coursing and Jointing in Rubble Stone MasonryFor squared or random rubble stone masonry, it is essential to incorporate coursing at regular intervals not exceeding 450mm to maintain structural integrity and a consistent appearanceCheck that rubble masonry is regularly coursed within 450mm vertically and that wall ties are correctly specified and installed for the wider joint widths. | 450 mm | Maximum |
| Lintel end bearing lengthMasonry openings — confirm against the lintel manufacturer's schedule for the specific span and loadMeasure the bearing at both ends before the opening is closed up, and check the bearing masonry is solid, level and fully bedded. | 100 mm for spans up to 1200 mm; 150 mm for longer spans | Minimum |
| Lowest fixing position for strapsFor any structural strap, the lowest fixing into the masonry or supporting structure must be positioned no more than 150mm from the bottom of the strapMeasure the distance from the bottom of the strap to the centre of its lowest fixing. | 150 mm | Maximum |
| Nominal mortar joint thicknessBrick and block masonry laid to a gauge rod.Check the gauge rod against the course heights at each lift; drifting joints show up badly on a long elevation. | 10 mm nominal | Exact |
| Residual clear cavity width with partial fill insulationMasonry cavity wall with partial fill insulation boardCheck the residual cavity at each lift with a gauge, and confirm retaining clips hold the boards tight to the inner leaf. | 50 mm | Minimum |
| Temperature limits and protection for masonryBrickwork and blockwork should generally not be laid when the air temperature is below 3°C and falling; work can resume when temperatures rise to 1°C with an expectation of exceeding 3°CVerify air temperatures are suitable for masonry work, materials are unfrozen, and new masonry is adequately protected by covers and insulation. | 3 °C | Exact |
| Wall tie embedment and slopeWall ties are critical for connecting masonry leaves and must be long enough to achieve proper embedment into both leaves, typically a minimum of 50mm in the mortar bedEnsure wall ties are of the correct length, embedded at least 50mm into mortar beds in both leaves, and installed sloping outwards. | 50 mm | Minimum |
| Wall tie embedment into each masonry leafCavity walls built with ties to a suitable length for the cavity width.Check the tie length against the cavity width before the leaf is closed up, and look along the course for ties sloping the wrong way. | 50 mm | Minimum |
| Wall tie spacing at reveals and movement jointsWithin 225 mm of an unbonded vertical edge — reveals, movement joints, wall endsCheck every reveal on each lift. Ties should be visible in the perp adjacent to the closer before insulation and cavity closers are fitted. | Additional ties at 300 mm vertical centres within 225 mm of the opening | Maximum |
| Wall tie spacing in a standard cavity wallMasonry cavity wall, cavity width up to 100 mm, wall height up to 15 mCount ties per square metre on each lift before the cavity is closed. Check ties are level or fall slightly to the outer leaf and that drip features point downwards. | 900 mm horizontally, 450 mm vertically (2.5 ties per square metre) | Maximum |
| Weep hole spacing above a cavity trayOver lintels, cavity trays and at the base of the cavityCount weep holes over each opening as the outer leaf is built. They must sit in the course immediately above the tray, not one or two courses higher. | 900 mm maximum centres, with at least two weep holes over every opening | Maximum |
0 of 22 ticked — saved on this device
Check cavity width is maintained at minimum 50mm (or as designed) and clear of mortar droppings (NHBC 6.1)
NHBC 6.1Verify wall ties installed at correct centres (900mm × 450mm max) and slope outwards to outer leaf (NHBC 6.1)
NHBC 6.1Check scaffold ties have not damaged cavity insulation or cavity trays (NHBC 6.1)
NHBC 6.1Verify insulation boards are tight-butted, clipped and continuous with no gaps at corners (AD L1A)
AD L1AConfirm DPC is continuous, correctly lapped and at minimum 150mm above finished ground level (AD C)
AD CInspect lintels for correct specification, adequate bearing (min 150mm) and correct orientation (NHBC 6.5)
NHBC 6.5Check cavity trays are dressed correctly with stop ends and weep holes at max 900mm centres (NHBC 6.1)
NHBC 6.1Check window and door reveals — DPC, insulation returns and cavity closers correctly installed (NHBC 6.1)
NHBC 6.1Confirm render carrier board, mesh and bellcast bead installed correctly where specified (NHBC 6.11)
NHBC 6.11Verify blockwork bond pattern is correct with perpends filled and coursing level (NHBC 6.1)
NHBC 6.1Check coursing gauge is consistent and within tolerance (±3mm per course) (NHBC 6.1)
NHBC 6.1Confirm movement joints are positioned per design and filled with compressible filler + sealant (NHBC 6.1)
NHBC 6.1Confirm correct mortar designation is used and protected from frost and rapid drying (BS EN 1996)
BS EN 1996Check wall plate straps are fitted at correct centres (max 2m) and properly embedded (AD A)
AD AConfirm head restraint straps fitted to gable walls at correct centres (AD A)
AD AVerify first floor joist hangers are correct specification and fully engaged into masonry (NHBC 6.4)
NHBC 6.4Verify that any steel beams or columns have correct fire protection and bearing plates (AD B)
AD BConfirm balcony / bay window construction matches structural engineer details (NHBC 6.9)
NHBC 6.9Verify party wall construction matches Robust Details or approved drawing for sound separation (AD E)
AD EConfirm fire stopping at party wall / separating wall junction with roof is complete and continuous (AD B)
AD BVerify meter box positions and service penetrations are correctly sealed and fire-stopped (AD B)
AD BCheck subfloor ventilation (suspended floors) or radon sump pipework is correctly installed (AD C)
AD CBrickwork and blockwork are on show for sixty years. Most of the finish problems come from what happened to the wall between lifts, not from the laying. No inspector will fail the visit on these — they are the difference between a plot that passes and a plot that hands over clean.
Cover the wall head at the end of every shift
Rain into an unfinished wall causes efflorescence, saturated insulation and lime staining that no amount of cleaning fixes.
When: Every day, and before any forecast rain.
Cover party wall and separating wall insulation before you leave it
Wet acoustic insulation loses performance and takes weeks to dry, and it is a certain sound test problem.
When: End of shift, every shift.
Keep the cavity clean and clear the base
Mortar snots bridging the cavity is the classic penetrating damp callback and it is invisible once the wall is up.
When: Lift by lift, with a cavity board.
Protect formed reveals, corners and cills as soon as they are built
Chipped arrises and stained cills are handover snags that require a brick to be cut out.
When: Immediately after building, until the scaffold comes down.
Keep the scaffold boards clear of the wall face
Boards tight to new brickwork drip dirty water down the elevation and leave a tide line the customer will see.
When: At every lift.
Clean down as you go rather than at the end
Fresh mortar comes off with a brush. Set mortar needs acid, and acid burns the brick face.
When: Same day.
291 inspection points that apply at the superstructure stage, each written in our own words from openly published guidance, with how to check it on site and what counts as acceptable. Use the checklist above on the day and this register when you need to settle a detail.
Mortar snots bridging the cavity
The single most common damp defect. Use a cavity batten, lift it every course or two, and clean the tray before the tray is buried.
High — water penetration claims are the most expensive Buildmark category.
Cavity trays without stop ends
A tray with open ends discharges water into the cavity instead of out through the weeps. Stop ends and weeps get inspected together, so fit them together.
High — structural, and only fixable by taking down brickwork.
Ties at the wrong centres around openings
Ties must be doubled up within 225mm of a reveal or movement joint. The field of the wall is usually right; the edges are where it fails.
Medium to high — invisible once the cavity is closed.
DPC below finished ground level
Levels move after the shell goes up. Check DPC height again once external levels are set, not just at the time of laying.
Medium — usually a rebuild of a small area if caught early.
ProPlot's audit tool includes these superstructure checks as interactive helpers — tick items off, attach GPS-stamped photos, and share the report with your inspector in one tap. Free while in beta.
The key stage inspection sequence on a typical UK housing plot.
Excavation & foundations
21 checks →
Drainage
20 checks →
Basement / lower ground
28 checks →
Ground Floor & Slab
19 checks →
Timber Frame Erection
21 checks →
Roof
22 checks →
Windows and External Doors
24 checks →
Insulation & Airtightness
23 checks →
First Fix
28 checks →
Fire Stopping
22 checks →
Pre-Plaster
21 checks →
Second Fix
31 checks →
External Works & Pre-Handover
23 checks →
Pre-handover
22 checks →
General Quality
20 checks →
Snag lists with GPS photo evidence
How to record and close out defects with evidence that stands up at handover.
NHBC stage inspections on site
Running key stage inspections and keeping the paperwork straight.
Build programme scheduling
Generating and maintaining plot-by-plot build programmes.
BREL report photo requirements
What Part L photographic evidence has to show, and when.
Our free, cited reference library — critical dimensions, build stage guidance, common defects and plain-English guides.
Discover how ProPlot covers every corner of UK site management.
Part L photographic evidence requirements.
Cut evening admin and automate reporting.
Build, slip and share 52-week programmes.
NHBC inspections, Part L evidence and audit trails.
Offline audits, GPS snagging and contractor portals.
Get practical tips for UK site managers — programme hacks, compliance shortcuts and feature updates. No spam.